LEON HURSE DAM & SPILLWAY
Crews made significant progress on the dam and spillway, finishing most of the project’s dirt and concrete work. Progress details:
- Dirt work: Nearly finished, with a total of 5 million cubic yards of soil.
- Spillway (to release water downstream): To be completed early next year.
- Soil cement protection: 46 percent added as a protective layer on top of the dam.
- Intake tower: Almost finished, with pipes to be added in 2026.
THE WATER CONVEYANCE SYSTEM (From Lake to Treatment)
The conveyance system was mostly completed this year. Progress details:
- Pipeline: Completed, undergoing testing and commissioning.
- Pump station building: Completed, undergoing testing and commissioning.
- Balancing Reservoir: Earthwork and major structures mostly finished, with final completion in early 2026.
- Full System Testing: The entire water delivery system is undergoing final testing.
LAKE ADMINISTRATION & VISITOR BUILDINGS
The maintenance building is complete, and designs for the Lake Ralph Hall Visitor Center and Office were finalized. Progress details:
- Lake Visitor Center/Office: Designs were finalized in 2025, with plans to break ground in early 2026. Parking lot construction started this winter.
- Maintenance Building: Built from the ground up this year.
MITIGATION & RECREATIONAL OFFERINGS
Environmental improvements (mitigation) construction to be completed in early 2026, beginning the required seven years of monitoring. Construction of public lake access points began in late 2025, with completion scheduled for early 2027. Progress details:
- Stream Restoration: Ninety percent of the restored streams are flowing, with vegetation and trees taking root. Remaining streams and planting will be completed in early 2026.
- Permanent Ladonia Fossil Park: Constructed this year, including river access, parking, fencing, and a pavilion. Hosted first Fossil Day celebration.
- Shoreline Management Plans/Recreational Lake Access: Draft shoreline management plans drafted, and public access areas being planned.
- Boat Ramps & Fishing Jetty: Boat ramp locations were selected and construction is underway. The fishing jetty is already completed.
LOOKING AHEAD
Lake Ralph Hall is well on its way to securing a long-term, reliable water supply for generations to come. Both the dam and water delivery system are nearly finished, with the lake on schedule to begin filling in 2026 and delivering water later in the year. Recreation and public access will open later, once the lake is filled and safe for recreational use. |