The project required temporarily shutting down the Irving Pipeline (which supplies water to Upper Trinity and Irving), the Harpool Water Treatment Plant, and the Chapman Lake Pump Station. During the shutdown, the treatment plant relied on stored water, and crews completed other key maintenance while this infrastructure wasn’t in use.
“This was a huge operation that took a month of planning in advance and close coordination across all teams,” said Ed Motley, Lake Ralph Hall Program Manager. “Our team worked 14-hour days in freezing rain to get the job done. They were very dedicated and did a great job.”
Crews only took a few days to install the new connection and air-test it for future use. Despite a short delay in pouring concrete (due to freezing temperatures), the connection was backfilled and flowing within the week. |